RELY · Case Study · On-site kitting and packagingMANAGED ON-SITE PRODUCTION

ON-SITE KITTING & PACKAGING · TWO SHIFTS · CONSUMER FOOD-STORAGE SETS

Delays squeezed the window. Two shifts held the retail dates.

Upstream delays compressed the schedule, then a labeling requirement was added mid-run. RELY ran and supervised on-site kitting across two shifts, built the new label into production, and held the delivery timeline.

Front page of the On-Site Kitting and Packaging case study PDFView the original PDF
  • 132,115Kits assembled on-site
  • 7,040Kits in one day, across two shifts
  • 1,056,920Bowls and lids8 per kit
  • HeldDelivery timelineAfter a label was added mid-run

The window shrank. The requirements kept moving.

A Wisconsin injection molder needed four-bowl, four-lid food-storage kits packed inside its own facility for a consumer brand's retail program. Upstream delays used most of the schedule before full-rate kitting.

HOW RELY HELD THE DATES

Jan to Jun 2026
  1. 01

    Stopped and started

    Paused and restarted on the customer's schedule as components arrived.

  2. 02

    Added the label

    Walked placement and labor first, then built the audit label into the running line.

  3. 03

    Validated, then restarted

    A 1,120-kit labeled run passed audit before full-rate restart.

  4. 04

    Ran two shifts

    Added a 2nd shift with its own RELY lead when the window compressed.

The requirements moved. RELY moved with them.

MANAGED WORK, NOT ADDED HEADCOUNT

Inside the customer's facility
  1. Supervision on both shiftsA RELY lead on each shift, with a RELY production manager supporting execution.
  2. The kit itselfFour bowls and four matching lids per carton, then downstream packaging.
  3. Validation and restartValidation runs into production, including the audited labeled restart.
  4. Two-shift output44,135 kits produced on two-shift days, with the labeled process running on both shifts.
  5. Line reviewIdentified where equipment, materials and pallet handling slowed output, and recommended fixes.
  6. Shared gainsOn this program, RELY passed efficiency gains back to the customer as the line got faster.

FULL PROGRAM · JAN 13 TO JUN 10, 2026

Kits, highest recorded week
31,518
Recorded production days
35

THE OUTCOME

The brand's retail timeline held.

Highest recorded day: 7,040 kits across two shifts. The added label did not extend the delivery timeline.

SOURCE: RELY INTERNAL PROGRAM RECORDS, JAN 13 TO JUN 10, 2026: 35 RECORDED PRODUCTION DAYS, INCLUDING VALIDATION RUNS. PRODUCTION DAYS ARE RECORDED DAYS, NOT CONSECUTIVE CALENDAR DAYS. CUSTOMER NOT NAMED. RESULTS REFLECT THIS PROGRAM ONLY AND ARE NOT A STANDARD LEAD-TIME OR CAPACITY COMMITMENT.